Chinese New Year 2027: How to Plan Your Orders in China
Every year, Chinese New Year stops a large part of production for much longer than the official public holidays. For a European SME or mid-sized company that sources in China, this is not a calendar formality: it is often the period that decides whether the goods leave before the break, or only arrive in the warehouse in the spring.
In 2027, Chinese New Year falls on Saturday 6 February. The official holiday runs from 5 to 13 February. At the end of November 2026, there is still time to decide clearly: attempt a last shipment before the break, or organise post-holiday production now and protect your first-quarter stock.
Eurasia Consultis is a mid-size, human-scale sourcing and trading partner, designed for medium-sized companies. We do not manufacture the products. We help our clients lock the schedule with the factories, plan inspections and coordinate logistics around this sensitive period.
The official dates of Chinese New Year 2027
The State Council published the official 2027 public-holiday calendar on 5 November 2026. For the Spring Festival, the useful points to remember are the following:
- the first day of the lunar year falls on Saturday 6 February 2027;
- the official holiday runs from Friday 5 February (New Year’s Eve) to Saturday 13 February 2027, that is nine days;
- Sundays 31 January and 14 February 2027 are make-up working days.
A shorter holiday comes before this period: the Gregorian New Year, from 1 to 3 January 2027. It can slightly slow follow-ups at the very beginning of the year, just before the final production rush.
These official dates are the starting point. On their own, they do not describe what actually happens in the factories.
What these dates really change in the factories
Many workers travel back to their home provinces for what is often their only long holiday of the year. Departures therefore start well before 5 February, and the restart takes place gradually after the 13th.
In practice, the following pattern is often observed, with variations by region and by factory:
- a few weeks before the holiday, factories speed up to finish orders already committed. Slots fill up, and some accept more work than they will actually be able to deliver;
- about two weeks before, some of the workforce starts to leave. Output drops, and trucks and export formalities become harder to obtain;
- during the official holiday, most factories are closed. Contacts reply little, sometimes not at all;
- after reopening, staffing is not always complete. Full capacity often returns after the Lantern Festival, around 20 February 2027, and sometimes later.
There is no single shutdown date that applies to the whole of China. The only reliable date is the one your factory confirms in writing, together with the restart date and the point at which it expects to return to normal capacity.
Why you should plan your orders now
At the end of November, the calendar is tightening. For a standard production already sampled, with materials available and a lead time of four to six weeks, a shipment before the break may still be possible, provided the purchase order, the deposit and the inspection window are locked immediately. For a new product, a customised model or a first run, it is often more realistic to aim for production after the holiday.
This applies as much to furniture and home-equipment projects as to building materials, garden, pool and sports goods or industrial machinery and equipment. As soon as the manufacturing lead time gets longer — doors, flooring, outdoor slats, padel courts or made-to-plan machines — the risk of missing the pre-holiday window increases.
The most useful step now is not to hope that “it will still go through”. It is to decide: what can still leave before mid-January, and what should be planned for March or April, with safety stock to last until then.
A practical calendar for 2026-2027
This calendar is a working guide, not a rule. It should be brought forward or pushed back according to the real lead time of your product, the volume and the freight forwarder. The idea is to work back from the date the factory slows down, not only from 6 February.
| Period | What is useful to do |
|---|---|
| Late November 2026 | Decide between a pre-holiday shipment and post-holiday production. Lock the specifications, the approved sample and, if the window is still open, the purchase order and the deposit. |
| December 2026 | Obtain in writing the shutdown, restart and return-to-full-capacity dates. Confirm what will actually be finished before the break. Book freight as soon as the production-completion date is solid. Finalise the export packaging. |
| Early January 2027 | Schedule the inspection before teams start leaving. Allow enough time for a rework if a lot is rejected. Anticipate the short holiday from 1 to 3 January. |
| Before mid-January 2027 | Aim for the last realistic loadings. Beyond that point, factories, road transport and shipping-line cut-offs tighten sharply. |
| 5 to 13 February 2027 | Official holiday. Do not count on an operational follow-up during this period. |
| Late February to March 2027 | Check who has actually returned, obtain a new schedule, and inspect early the first productions after the holiday. |
If an order cannot be finished properly before the break, it is better to decide that in December than to force a shipment in the rush of January.
If you are still aiming for a shipment before the holiday
This option remains credible mainly when several conditions are met: the product is already locked, the sample is approved, materials are available, the remaining production lead time is short, and an inspection can take place early enough to correct a discrepancy before teams leave.
In that case, the schedule is built backwards: vessel or groupage departure date, port cut-off, loading, inspection, end of production, then the latest launch date. Follow-up after the purchase order then becomes as important as the negotiated price.
If one of these steps is missed, it is better to switch in time to post-holiday production than to receive, in Europe, a lot shipped too quickly.
If you are planning production after the holiday
For many projects, this is now the soundest scenario. It still requires just as much method.
First, protect the first quarter: what volumes do you need to have in stock, or already at sea, to serve your customers until the next wave arrives? Next, warn your contacts in Europe of a longer lead time, rather than discovering it in February. Finally, plan a close inspection of the first productions after the restart: staff change, machines start up again, and this is often when discrepancies reappear.
This organisation is part of project management as much as of the purchase itself.
The points to lock in writing with the factory
Before treating the calendar as settled, several points deserve written confirmation, and not only an informal exchange of messages:
- the precise shutdown and restart dates, and the date on which the factory expects to return to normal capacity;
- the quantity that will actually be finished before the break, distinct from the quantity originally promised;
- the inspection window, and what will happen to a non-conforming lot if teams are already leaving;
- the packing, readiness and loading dates;
- the person who can be reached, if there is one, during the holiday.
These points avoid the classic misunderstanding: a “production finished” date announced in January that turns out to be an intention, not goods ready to be inspected and loaded.
The questions to ask this week
A few simple questions often give a clearer picture than a schedule that is too general:
- On what exact date does the factory plan to stop production, and on what date will the effective restart take place?
- When does it expect to return to normal capacity, beyond a simple reopening?
- For your order, what quantity can actually be finished, inspected and loaded before the shutdown?
- What is the latest possible date to launch production if you are still aiming for a departure before the holiday?
- Which inspection slot can be reserved, and what happens if the lot is not conforming when teams are about to leave?
- Is the announced date a confirmed end of production, or only an intention, with no pickup or freight space actually planned?
The answers, ideally in writing, then serve as a common basis between the buyer, the factory and the logistics partners.
Quality and logistics: two points to watch
Quality control cannot be postponed until after reopening if you still want to ship before the holiday. A lot rejected in mid-January has very little chance of being reworked in time. Factory audits and quality control should therefore be planned at the same time as production, not at the last minute.
Logistics often tighten even before the lines stop: less space on vessels, earlier cut-offs, trucks harder to find, then, after the holiday, departures sometimes cancelled for lack of volume, before a new bottleneck. Logistics support at this stage mainly means booking early and starting from a date when the goods are truly ready, rather than from an optimistic date.
These calendar shocks come on top of the more general uncertainties of shipping. Anticipating them does not remove the risk; it avoids discovering a second, predictable one on top of the first.
How a sourcing partner can help you
ECI is not a manufacturer, not a freight forwarder, and not a customs broker. Our role, for a mid-sized company, is to bring order back to the calendar: compare the factories’ real capacities, align the specifications and quantities with what is feasible, follow production, place inspections at the right time and coordinate the work with logistics partners.
This is particularly useful when several product families are moving forward in parallel, or when a first sourcing and trading project has to get through this period without shifting an entire commercial season.
Planning for Chinese New Year means protecting your lead times
6 February 2027 is not a surprise: the official dates are known, and so is the typical behaviour of factories around this holiday. What makes the difference, for a European importer, is deciding now what leaves before the break, what waits for the restart, and what must be inspected or booked early enough for those dates to hold.
If you are preparing an order in China around Chinese New Year 2027 and would like a clearer view of the schedule, inspections and logistics, tell us about your project.
Yoan, as well as Jean, President of Eurasia Consultis, will be glad to discuss it with you.
ECI – Your sourcing partner in China.